Eastbourne College, East Sussex

We were awarded the contract by VINCI Construction to carry out the installation of the Silka Elements at their College development.

 

We installed 2,500m2 of 150mm and 215mm elements over the 3 storeys of the classroom block.

Precast concrete floors where then placed on to the walls at each level. All works including the floor installation took 7 weeks to complete.

 

“We achieved optimal results from designing a building with the system in mind rather than adapting a design intended for another methodology.” Mike Rosier, Senior Project Manager, VINCI Construction UK Ltd.

 

Click here to view the Eastbourne college timelapse video

 

Take a look at these great before and after shots of the building.

 