  • The Client’s View – Tonbridge Extra Care Housing Project

     

    Tonbridge Progress(2)

    This week we caught up with Jenner Contracts Manager, Michael Withers for a mid-programme review. We’re now 20 weeks into the 26 week programme and whilst we’re on schedule and satisfied with the progress and results we’re seeing, we always like to engage the client on a regular basis, and at a higher level than the day to day build process. Here’s what Michael had to say about the project to date;

    “Initially we were looking at a traditional masonry solution for the project, however due to time constraints and a firm handover deadline set by the customer, we approached MFS to discuss alternative build methods which could significantly reduce the build programme.

    As well as shaving over 3 months off the programme, a huge factor for us was the management role that MFS would provide, effectively taking over the whole superstructure build, including being involved in the design and co-ordination. Their early involvement with our Design Manager has been fundamental to the project delivery. Jenner have been able to take an overseeing role from an architectural and structural engineering standpoint with MFS managing the build.

    The other key benefits have been the lack of waste on site and the fact less internal scaffold is required. The project has opened our eyes to the potential this method has, especially in terms of being less reliant on labour due to the more mechanical system. That said, we were also impressed by the Dutch labour installers who MFS brought over from Xella (Silka block system manufacturers). Their experience and pace of working on site showed us how, given time, this system could overtake traditional methods in the UK.

    The block build process and the Silka material itself (which can be used in all weather conditions), not only improve the build programme timeframe, they also support the sustainability and efficiency values. We’re working towards a BREEAM certification for the project, with sign off already received from NHBC and Building Control. We’re just waiting on the sound rating for the internal walls since these have only been tested in a factory and not on site.

    In all, the potential is great. With more skilled labour in the UK and more testing on site, rather than in factory conditions, this method ticks all the boxes.”

    Whilst we don’t want to tempt fate, we’re confident that we’ll continue on programme and will deliver on the planned 26 weeks, if not before, and we look forward to sharing the final reports from both client and end-user.

    If you would like to find out more about the team here at MFS and how we can make your build project more efficient, or if you just want to know more about Silka Elements, speak to a member of our team today.

    This entry was posted in General News. Bookmark the permalink.

    Comments are closed.

  • Thin Joint Factsheet

    Everything you need to know about thin joint

    A full explanation of thin joint blockwork and related areas. The perfect guide to share with colleagues and managers.