Project Description

Ampersand Apartments

MFS were appointed to work with PDR Construction Ltd to deliver the full structural envelope for 118 apartments for Haxted Estates using the Xella Silka Element System, a very large format block manufactured and cut offsite.

Green Housing

‘A’ Rated
Finalist for the Constructing Excellence SECBE Offsite Award 2019.

Construction at a glance:

Location: Kenley in Surrey
ClientPDR Construction Ltd for Haxted Estates
Build TypeResidential High Rise
No of Units: 118 apartments, 4 storeys, over 5 blocks
Status: Completed Project
Build Duration: Completed October 2018, 32 weeks on site
MFS System: Xella Silka Element System
Awards: Finalist for the Constructing Excellence SECBE Offsite Award 2019

Additional build requirements:

  • Structural steel frame
  • Precast concrete floor planks
  • Balconies
  • Stairs & landings
Contact us

Project Details

Xella Silka Element System
Xella Silka Factsheet

We were excited to bring our management approach to a project of this scale. Using our experience and expertise in intelligent value engineering, we have developed innovative, cost effective solutions that meet the growing environmental demands of today’s housing industry and offer best value in the long term.

The client chose to adopt our alternative build methods due to a need to fast track the build. Use of the Silka Element system will provide efficiency in the project and the build process, not to mention the financial benefit of early occupation.

Finalist for the Constructing Excellence SECBE Offsite Award 2019.

Construction Achievements:

0 weeks
less time on site
0%
Reduction in Labour
0%
Less waste on site
0K
Overall build saving

Key Performance Indicators

Timescale

  • 26 weeks in planning and design

  • 12 weeks in Dfma

  • 32 weeks on site

Savings

  • Weeks less time on site than a traditional build

  • Significant reduction in overall build spend

  • 50% less labour required

  • 100% less waste on site

  • Reduction in defects and higher build accuracy

  • No internal scaffolding

  • Lower insurance risk and costs

  • Occupation weeks earlier than traditional builds

Performance

  • Fully load bearing: Up to 10 storeys

  • Thin Joint Mortar: Sets within 2 hours vs traditional 24

  • Fire resistant: Excellent 4hrs+

  • Acoustic: Excellent

  • Thermal: Good

  • Green Credentials: A rated

Compliance

  • Design Warranty for MFS design & builds

  • NHBC Approved and BBA Certified

  • Part E & Part L Building regs

  • Meets Approved Document A3 Disproportionate Collapse Class 2A & 2B

  • BIM compliant

  • Advanced and environmentally friendly manufacturing process

The Role of MFS

MFS were involved from the design and planning stage to the delivery of the complete structural envelop for these apartments. Our Design Warranty was supplied.

Finalist for the Constructing Excellence SECBE Offsite Award 2019.

MFS Design Innovations

The P.C.C cantilever balconies were designed by MFS and their Design Team and installed as the floor planks were being installed. Saving time, money and the hassle of installing the balconies at a later date. This solution is a 1st within the industry.

Client Testimonial

Managing QS – London commented “We’ve got the best solution and best people to deliver it”

PDR ConstructionJaymie Kelly, PDR Construction

Ampersand Apartments – Overview and Drone Footage

See all videos for Ampersand Apartments

Construction Image Gallery

Contact Masonry Frame Systems

Please tick this box if you would like to be kept up to date with our latest news and projects, you can unsubscribe at any time.

We’d love to discuss your construction project with you, please get in touch with us.

Connect with MFS