Eastbourne College
MFS were awarded the contract by VINCI Construction to carry out the installation of the Xella Silka Element System at their College development. We installed 2,500m2 of 150mm and 215mm elements over the 3 storeys of the classroom block. Each block is laid on thin joint mortar and is placed using a mini motorised crane. Precast concrete floors where then placed on to the walls at each level. All works including the floor installation took 7 weeks to complete.

‘A’
Rated
Construction at a glance:
Location: Eastbourne
Client: VINCI Construction for Eastbourne College
Build Type: Residential High Rise
No of Units: Several classrooms, over 3 storeys
Status: Completed Project.
Build Duration: Completed May 2016, 7 weeks on site.
MFS System: Xella Silka Element System
Additional build requirements:
- Structural steel frame
- Precast concrete floor planks
- Roof trusses


Project Details
Set in a beautiful location, the iconic Eastbourne College has taught many of the world’s great and good. The College decided to undergo a complete overhaul of their dining, sporting and recreational facilities. VINCI Construction UK won the £22.5 million project and were delighted to be working with them to complete aspects of the build.
We constructed primarily the new classroom buildings. Of which the key feature was the use of the Silka large format blocks to create the load bearing walls which are 25N in strength. Each block is laid on thin joint mortar and is placed using a mini motorised crane.
The whole development completed in may 2017 to fit in with the College’s plans to commemorate its 150 years since its founding.

We achieved optimal results from designing a building with the system in mind rather than adapting a design intended for another methodology.
MFS took over our Silka works on our Eastbourne College project after problems with our Belgian contractor.
Being an experienced thin bed contractor, MFS got to grips with the intricacies of the system including the critical sequencing of the build to access the works with the material handler. MFS invested in further training of their operatives in the system and equipment including material handling which was a grey area regards CPCS certification. There were some sequencing delays by other trades… but MFS proved to be flexible in accommodating.
Construction Achievements:
Key Performance Indicators

Timescale

Savings

Performance

Compliance
Construction Image Gallery
Contact Masonry Frame Systems



















