Tonbridge Extra Care Housing
MFS were appointed by Jenner Contractors Ltd of Folkestone who were looking for alternative build methods to deliver within a very tight timescale. MFS did just that using their i-Form Solution® utilising the Xella Silka Element system with Xella Ytong thin joint internal walls, completing the project in just 26 weeks.

‘A’ Rated
Finalist for the Constructing Excellence SECBE Innovation Award 2019
Construction at a glance:
Location: Tonbridge Extra Care Housing, Rosewell House, Tonbridge Kent
Client: Jenner Contractors Ltd
Build Type: Care Homes
No of Units: 59 apartments over 3 storeys
Status: Completed
Build Duration: 26 weeks on site, saving 17 weeks on overall build programme
Savings: 25% saving on overall construction costs
System: MFS i-Form Solution®
Awards: Finalist for the Constructing Excellence SECBE Innovation Award 2020
Construction Platfoms:
- Xella Silka Element System with Xella Ytong thin joint internal walls
- Structural steel frame
- Ytong thin joint internal walls
- Precast concrete floor planks and stairs
- Roof trusses


“As well as shaving over 3 months off the programme, a huge factor for us was the management role that MFS would provide, effectively taking over the whole superstructure build, including being involved in the design and co-ordination. Their early involvement with our Design Manager has been fundamental to the project delivery…with MFS managing the build. The block build process and the Silka material itself has improved the build programme timeframe, they also support the sustainability and efficiency values.”
Project Details
With severe time constraints and a very tight handover schedule, Jenner Contractors Ltd of Folkestone first approached us to discuss what alternative build methods we could put forward that would ‘fast track’ the construction shell, to significantly reduce the build programme with assured delivery.
After a fully consultative process, it was agreed that the MFS i-Form Solution® employing the Xella Silka Elements as the primary construction ‘platform’ offered the best opportunity to achieve the timescales.
MFS, in co-ordination with Xella, were engaged to construct the whole structural envelope of the 3 storey 59 apartment Extra Care Facility in just 26 weeks.
Finalist for the Constructing Excellence SECBE Innovation Award 2019
Construction Achievements:
Key Performance Indicators

Timescale

Savings

Performance

Compliance

The Role of MFS
MFS took a hands-on management role, effectively taking over the whole superstructure build, including being involved in the design and co-ordination. Their early involvement with Jenner’s Design Manager was felt to be fundamental to the successful project delivery using their trademarked i-Form Solution® methods and construction platforms – a PDfMA approach to MMC.

MFS Design Innovations
Finalist for the Constructing Excellence SECBE Innovation Award 2019

Client Testimonial
“As well as shaving over 3 months off the programme, a huge factor for us was the management role that MFS would provide, effectively taking over the whole superstructure build, including being involved in the design and co-ordination. Their early involvement with our Design Manager has been fundamental to the project delivery…with MFS managing the build.
The block build process and the Silka material itself has improved the build programme timeframe, they also support the sustainability and efficiency values.”
Construction Image & Video Gallery
Contact Masonry Frame Systems

















